Road Improvement Component
|
1.0 Road Improvement Component Overview |
This component will support the development of three major transport corridors by
widening and strengthening o f about 461 km State Highways (SH). The road corridors
and links were identified through the Strategic Options Study, which determined
their priority among all the state highways, and were subjected to economic analysis
to establish their economic viability.
The three corridors serve 10 districts, improve
transport connectivity to current and planned industrial and mining areas and tourist
locations, connect major National Highways and ports in Orissa and neighboring Andhra
Pradesh, and enhance the availability of transport services to poor and tribal communities
living along the comdors.
The current roads are mostly of single lane standard (3.5
meter), with some intermediate lane (5.5 meter) sections, and will be widened to
double-lane (7 meters), and will have 2.5 meter shoulders on each side for a total
road width o f 12 meters, except in some environmentally sensitive areas and heavily
built up locations, which will be designed and developed to minimize
environment
and social impacts.
The list o f roads to be taken up under the project is listed
in Table 1 below. In addition, the project will finance the cost o f repairing a
high-level bridge on the Bansadhara River, which was damaged during the August 2007
floods. The bridge (150 meter span) is located on one o f the project corridors
(Berhampur-Bangi Jn-Rayagada ) and will be reconstructed along with works for river
training, embankment and approach roads. |
| |
|
OSRP Major Transport Corridors |
| |
| |
| Corridor Name |
KM |
Road Link |
SH |
KM |
Districts Covered |
Jagatpur-Kendrapara-Chandbali-
Bhadrak- AnandPur |
201 |
Jagatpur-Kendrapara-Chandbali
|
SH-9A |
99 |
Cuttack,Kendrapara & Bhadrak |
| |
|
Chandbali-Bhadrak |
SH-9 |
53 |
Bhadrak |
| |
|
Bhadrak-AnandaPur |
SH-53 |
49 |
Bhadrak-Keonjhar |
|
Khariar-Bhawanipatna |
|
Khariar-Bhawanipatna |
SH-16 |
68 |
Kalahandi,Bolangir & Nuapada |
|
Berhampur-Bangi Jn-Jk Pur(Rayagada) Including reConstruction of flood damaged bridge(150
m) over Bansadhara river |
192 |
Berhampur-Banki Jn |
SH-17 |
150 |
Ganjam,GajaPati,Rayagada |
| |
|
Banki Jn-JK Pur(Rayagada) |
SH4 |
42 |
Rayagada |
| |
|
|
|
|
|
|
Total |
461 |
|
|
461 |
|
|
| |
| 1.1Pre-Investment Studies |
| |
The Government of Orissa have taken up the following activities as pre-investment
studies for the proposed project.
|
|
1) |
Consultancy Services for preparation of Feasibility Study and Detailed
Project Report preparation of Phase ? 1 Roads of Orissa State Roads Project
- M/s Consulting Engineers Group ( India) Ltd. has been engaged for this assignment.
|
|
2) |
Individual Consultant's Services for Facilitator to Task Force
for preparation of Institutional Strengthening Action Plan for Orissa Works Department
- Mr. V. Muraharireddy, Ex- E.I.C., PWD, Andhra Pradesh has been engaged for
this assignment. |
|
|
Public Investment |
| |
|
In this component the Government will borrow directly from the World Bank for the
cost of the Project. The list of the road packages identified by the Government
for improvement are as follows. |
|
|
|
Brief Description of Project Roads |
| |
|
Bhwanipatna to Khariar is of length
68 kms and is located in Kalahandi,Nuapada and Bolangir districts of Orissa. It
starts from Km 2/0( near Bhawanipatna) and
ends at Km 70/0(near Khariar) . The sub-project is a section of SH-16 and
is an important route connecting to NH-201 and NH-217. The existing road carriageway
is of single/intermediate lane, with the road badly damaged on some portions like
bridge approaches 8/600,10/537,20/979,27/650,27/949,28/928,29/239
due to overtopping
of flood water of
Tel River
in last monsoon. The bridges at locations 54/791 and 58/760 are under re-alignment.
The road traverses mostly through plain and rolling terrain and have mostly flat
gradient and good geometry. |
|
Bhadrak to Chandabali (Km 0/0 to Km 45/0
of SH-9) and Bhadrak to Anandapur (Km 0/0 to Km 50/0 of SH-53) are located in Bhadrak
and Keonjhar districts. The road stretch Bhadrak.-Chandabali starts at Bhadrak (0/0)
and ends at Chandabali (45/0). Bhadrak-Anandapur stretch starts form Kolkata-Chennai
4-lane highway (NH-5) at chainage 155/0.The Chandbali-Bhdrak-Anandapur stretch
traverses through plain terrain and has mostly flat gradients with good geometry.
The existing road carriageway is of single/intermediate lane,with the road badly
damaged in many locations especially at Nalagandha,Ghusura causeway portion (Km
36/005) in Bhadrak-Chandbali stretch. |
|
Berhampur to Taptapani road (Km 0/0
to Km 41/0 of SH-17) is of length 41 kms and is located in Ganjam district. This
stretch of road takes off form NH-217 at 18th Km near Berhampur. The
road traverses mostly through plains and has mostly flat gradients with good geometry.The existing carriageway width (7m is of single/intermediate lane. Major re-alignment
of the road section is proposed at Km 6/800 (R/S) to avoid sharp consecutive horizontal
curves. There are total 10 no.s of existing bridges, one of this is major and remaining
9 are minor bridges. Out of 9 minor bridges two at Km 11/270 and 29/500 are to be
reconstructed and the remaining seven are to be rehabilitated. Berhampur to Taptapani
section caters the needs of nearest town Digapahandi and it is also an important
road junction.
<<Back to Home |
| |
| 2.0 Status Of Year-1 Road Packages
2.1Widening and Strengthening of Existing Carriageway to 2 lane from Bhawanipatna to Khariar (SH-16)(Y1-P01)
Click here to See the photos of P01
|
| Agency |
M/s Patel– ARSS JV
Plot No. 38, Sector – A, Zone - D
Mancheswar Industrial Estate,
Bhubaneswar – 751 010 |
| Estimated Cost |
Rs. 103,43,94,251 |
| Contract Amount |
Rs.105,51,39,120 |
| Date of Commencement |
20.02.2009 |
| Date of Completion due |
19.08.2011 |
| Length Handed over to the Contractor |
|
| For Immediate Execution |
5 km on November, 2009 |
| 5 km on November, 2009 |
28 km on April 19, 2010
[ Km 35 – Km.63 ] |
Length Handed over to the Contractor :
For Immediate Execution
|
5 km on November, 2009
[ Km. 5/0 to Km. 6/500, Km. 14/0 to Km. 17/5 ]
|
MILE STONES as per Contract. : |
|
1st Milestone - Km.18/0 to Km. 46/0 of SH-16 : |
10 Months from the date of commencement of works i.e. till 19th Dec, 2009 |
2nd Milestone - Km.46/0 to Km.70/0 of SH-16 : |
20 Months from the date of commencement of works i.e. till 19th Oct, 2010 |
Completion of the whole work : |
30 Months from the date of commencement of works i.e. till 19th Aug, 2011 |
Revised Mile Stones proposed as per EOT |
|
1st Milestone Km.35/0 - 63/0 : |
28 Kms
|
2nd Milestone Km. 63/0 – 70/0 and 18/0 - 35/0 : |
24 Kms |
Completion of the whole work : |
16.0 Km |
TOTAL : |
68.0 Km. |
Interim Arrangements
One independent Executive Engineer of OWD has been designated as “Resident Engineer” for this package to administer the Contract as “Engineer”. Theme Engineering Services Private Limited was hired for assisting the Engineer in Construction Supervision. This interim arrangement shall continue till a regular Supervision Consultant is hired through Bank Procurement process.
- Er. Digambar Biswal : P01 Assisted by
[ Theme Engineering Services Pvt. Ltd., Jaipur ]
Theme Engineering Services Pvt. Ltd. has commenced its services with effect from 1st Nov, 2010. The Expenditure for this interim arrangement shall be borne by the Government of Orissa.
Items |
Provisions |
Upto-Mar, 2011 |
Upto April,2011 |
Financial Progress (Rs. Cr.) |
105.51 |
13.37 |
15.38 |
| Physical Progress |
Road |
68 km |
BC:2.0 km
DBM : 14.5 km
GSB : 16.0km |
BC:2.0 km
DBM : 14.5 km
GSB : 16.0km |
Tree Cutting (No.): |
2301 |
917 |
917 |
Land Acquisition (villages) |
41 |
40 |
40 |
R&R (PAPs) |
4.4km |
PAPs Asper RAP – 97 Nos (1st MS)
No.s after identification and verification:103 No.s
(1st MS)
Identification, survey, structure valuation, microplan, Bank A/c completed: 103 nos
PAPs Relocated:102
|
PAPs Asper RAP – 97 Nos (1st MS)
No.s after identification and verification:103 No.s
(1st MS)
Identification, survey, structure valuation, microplan, Bank A/c completed: 103 nos
PAPs Relocated:102
|
Utility Shifting : |
|
|
|
Pipeline shifting |
10050mtr |
4000 mtr completed |
4000 mtr complted |
Tube Wells |
52nos |
27 no.s |
27 no.s |
Electric Lines |
68 km |
55 kmcompleted |
55 km completed |
Bottleneck:
1. Work has been delayed due to extended rainy season till end Oct, 2010.
2. Decision on Suitability of existing primary item such as GSB (Granular Sub Base) and Hydraulic Model Study on river Tel awaited from Government.
<<Back to Home
2.2 Widening and Strengthening of Existing Carriageway to 2 lane from Chandbali – Bhadrak – Anandpur
(0/0 -45/0 km of SH-9 and 0/0 -50/0 Km of SH- 53)(Y1 P02) Click here to See the Photos of P02
| Agency : |
M/s SOMDATT Builders– ARSS JV
Plot No. 38, Sector – A, Zone - D
Mancheswar Industrial Estate,
Bhubaneswar – 751 010 |
| Estimated Cost : |
Rs. 194,31,12,992 |
| Contract Amount : |
Rs.216,23,17,622 |
| Date of Commencement : |
02.08.2011 |
Length Handed over to the Contractor :
For Immediate Execution |
17 km on November, 2009 |
| 1st Mile Stone : |
Rs. 194,31,12,992 |
Length Handed over to the Contractor :
For Immediate Execution |
5 km on November, 2009[ Km. 5/0 to Km. 6/500, Km. 14/0 to Km. 17/5 ] |
| MILE STONES as per Contract. |
1st Milestone –
SH -9 : Km.0/0 to Km.10/0 :
and Km. 25/0 – 41/0 |
10 Months from the date of commencement of works, i. e. till 2nd Dec 2009
i.e. till 21st July, 2009 |
2nd Milestone –
SH -9 : Km.10/0 to Km.25/0 of SH-9
and SH – 53 Km. 27/0 to Km. : 45/0 |
20 Months from the date of commencement of works i.e. till 2nd Oct, 2010 |
| Completion of the whole work |
30 Months from the date
of commencement of works
i.e. till 2nd Aug, 2011 |
| Revised Mile Stones proposed as per EOT |
1st Milestone
SH – 9 : Km. 2/0 - 30/0,
SH – 53: Km. 12/0 – 17/0, 21/0 – 26/0
and Km 32/0 – 39/0 :
[ Less builtup area 10.3 kms ] |
34.7 Kms |
2nd Milestone
SH – 9 : Km. 30/0 – 45/0
SH – 53: Km. 0/0 - 12/0, 26/0 – 32/0 :
[ Less built-up area 4. 5 kms ] |
28.5 Kms |
Completion of the whole work
SH – 9 : Km. 0/0 – 2/0
SH – 53: Km. 39/0 – 42/3 including
builtup areas leftout :
Addl. : Km. 42/3 to NH-215 Jn. (1.8 Kms).
Dropped: Km. 42/3 – 50/0 of SH – 53 |
25.90 Km |
| TOTAL : |
89.1 Km. |
Interim Arrangements
One independent Executive Engineer of OWD has been designated as “Resident Engineer” for this package to administer the Contract as “Engineer”. Theme Engineering Services Private Limited was hired for assisting the Engineer in Construction Supervision. This interim arrangement shall continue till a regular Supervision Consultant is hired through Bank Procurement process.
- Er. Sasanka Sekhar Das: P02 Assisted by [ Theme Engineering Services Pvt. Ltd., Jaipur ]
Theme Engineering Services Pvt. Ltd. has commenced its services with effect from 1st Nov, 2010. The Expenditure for this interim arrangement shall be borne by the Government of Orissa.
Items |
Provisions |
Upto Feb-2011 |
Upto Mar -2011 |
Financial Progress (Rs. Cr.) |
216.23 |
21.58 |
24.32 |
Physical Progress |
Road |
95 Km |
BC:7.12 km
DBM : 17.345 km
GSB : 19.33km |
BC:7.12 km
DBM : 17.345 km
GSB : 19.33km |
Tree Cutting : |
7299 |
3645 |
3645 |
Land Acquisition |
79 villages |
74 village |
74 villages |
R&R |
30.6 Km |
PAPs Asper RAP –158 Nos (1st MS)
No.s after identification and verification:272 No.s
(1st MS)
Identification, survey, structure valuation, microplan, Bank A/c completed: 263 nos
PAPs Relocated:172
|
PAPs Asper RAP –158 Nos (1st MS)
No.s after identification and verification:272 No.s
(1st MS)
Identification, survey, structure valuation, microplan, Bank A/c completed: 263 nos
PAPs Relocated:172 |
Utility Shifting : |
|
|
|
Pipeline shifting |
17,220 mtr |
4000 mtr completed |
4200 mtr completed |
Tube Wells |
88 nos
[ 62+26] |
46 no.s |
46 nos |
Electric Lines |
SH 53: 39.5 km
SH 9: 50 km
Total: 89.5 km |
55 kmcompleted |
55 kmcompleted |
Bottleneck:
1. Work has been delayed due to extended rainy season till end Oct, 2010.
2. Decision on Suitability of existing primary item such as GSB (Granular Sub Base) awaited from Government.
<<Back to Home
2.3 Widening and Strengthening of Existing Carriageway to 2 lane from Berhampur – Taptapani ( SH-17 )Y1- P03
Click here to See the Photos of P03
Agency: : |
M/s BACKBONE – ARSS JV
Plot No. 38, Sector – A, Zone - D
Mancheswar Industrial Estate,
Bhubaneswar – 751 010 |
Estimated Cost : |
Rs. 75,33,96,605 |
Contract Amount :
|
Rs. 81,97,23,707 |
Date of Commencement : |
22.11.2008 |
Date of Completion Due : |
21-11-2010 |
Length Handed over to the Contractor :
For Immediate Execution |
4.0 Km on November, 2009
|
1st Mile Stone : |
18.580 Km on dated 07.05.2010 |
Length Handed over to the Contractor :
For Immediate Execution |
5 km on November, 2009
[ Km. 5/0 to Km. 6/500, Km. 14/0 to Km. 17/5 ] |
MILE STONES as per Contract. |
|
1st Milestone - Km.2/0 to Km.15/0 of SH-17 : |
8 Months from the date of commencement of works
i.e. till 21st July, 2009 |
2nd Milestone - Km.15/0 to Km.30/0 of SH-17 : |
16 Months from the date of commencement of works i.e. till 21st March, 2010 |
Completion of the whole work : |
24 Months from the date of commencement of works i.e. till 21st Nov, 2010 |
Revised Mile Stones proposed as per EOT |
1st Milestone Km.5/0 - 18/0, 37/0 – 41/0 :
[ Less builtup area 4kms ] |
13 Kms
|
2nd Milestone Km. 0/0 - 3/0, 18/0 – 23/0
and 25/0 – 37/0.[ Less built-up area 5 kms ] : |
15 Kms |
Completion of the whole work : |
13.0 Km |
TOTAL : |
41.0 Km. |
Interim Arrangements
One independent Executive Engineer of OWD has been designated as “Resident Engineer” for this package to administer the Contract as “Engineer”. Theme Engineering Services Private Limited was hired for assisting the Engineer in Construction Supervision. This interim arrangement shall continue till a regular Supervision Consultant is hired through Bank Procurement process.
- Er. Manoranjan Misra : P03 Assisted by
[ Theme Engineering Services Pvt. Ltd., Jaipur ]
Theme Engineering Services Pvt. Ltd. has commenced its services with effect from 1st Nov, 2010. The Expenditure for this interim arrangement shall be borne by the Government of Orissa.
Items |
Provisions |
Upto Feb-2011 |
Upto Mar- 2011 |
Financial Progress (Rs. Cr.) |
81.97 |
8.59 |
9.50 |
Physical Progress |
Road (km) |
41 |
BC:0 km
DBM : 5.4 km
GSB : 6.4 km |
BC:0 km
DBM : 5.4 km
GSB : 6.4 km |
Tree Cutting : |
1348 |
644 |
645 |
Land Acquisition: |
31 villages |
28 village |
28 village |
R & R |
11.7 Km |
PAPs Asper RAP –338 Nos (1st MS)
No.s after identification and verification:147 No.s
(1st MS)
Identification, survey, structure valuation, microplan, Bank A/c completed: 118 nos
PAPs Relocated:62
|
PAPs Asper RAP –338 Nos (1st MS)
No.s after identification and verification:147 No.s
(1st MS)
Identification, survey, structure valuation, microplan, Bank A/c completed: 118 nos
PAPs Relocated:62
|
Utility Shifting : |
|
|
|
Pipeline shifting |
21,040 mtr |
10,210 mtr completed |
10,210 mtr completed |
Tube Wells |
46 nos |
42 no.s |
42 no.s |
Electric Lines |
41 Km |
26 kmcompleted |
26 kmcompleted |
Bottleneck:
- Work has been delayed due to extended rainy season till end Oct, 2010.
- Decision on Suitability of existing primary item such as GSB (Granular Sub Base) awaited from Government.
<<Back to Home
3.0 Construction Supervision Consultancy for Balance Works(Year-1)
- Expression of Interest was issued in CE’s No. 41098 Dt. 21.09.2010.
- Till last date of submission, 22 Firms submitted their proposal, which are under scrutiny for shortlisting.
- Draft Request for Proposal and Terms of Reference for this assignment along with the Cost Estimate was submitted to the World Bank for their review and comments. World Bank in its Email Dt. 1st Nov 2010 has forwarded its comments for incorporation and submission to Bank along with the shortlist for their clearance.
<<Back to Home
|
| 4.0
Land Acquisition Status |
| |
|
ORISSA STATE ROADS PROJECT(YEAR-I) TABLE FOR 6(1) NOTIFICATION AS ON 28.05.2011 |
Name of the Project corridor
with Stretch |
Name of the District |
Total nos villages of each corridor with 4(1) noti.
For 6(1) purpose
|
Total
nos of proposals received by the PMU and
estimate sanctioned by CE(WB) and sent to Revenue & Disaster
Management Deptt.
|
Total amount sanctioned in Rs.and paid to LAOs
for 6(1) notification with the number of villages. |
Total nos of villages
notified under Section 6(1) by Govt in Revenue Deptt.
as per available records. |
Govt.
in Revenue & Disaster Management Deptt's direction to the
Collectors & District Magistrate to go ahead with the Acquisition
of Land under Section-7. |
Pocession handed over to Works Dept. |
Total Area Acquired (in Acres) |
| Area of Notification |
Bhawanipatna-Khariar
Road, SH-16 - 68kms
|
Kalahandi |
19 |
19 |
Rs 5893160.00
19 Villages |
19/
32.42 |
19 Nos of Villages |
19 no. of villages handed over |
|
| Bolangir |
13+1 |
13 |
Rs. 5154541.00
13 Villages
|
13/
28.50 |
13 No. Of village |
12 villeges handedover |
1-New |
| Nuapada |
9 |
9 |
Rs. 61,53,772.00
9 Villages |
9/
8.65 |
9 no of villages |
9 villageshandover |
|
(A) Bhadrak-Chandbali
Road, SH-9(45Kms)
|
Bhadrak |
48+2 |
48 |
Rs. 40306640.00
48 Villages |
48/
29.13 |
48 nos. of villages |
48 vill. possession handed over(5-protest) |
|
(B) Bhadark-Anandpur
Road, SH-53(50 kms) |
Bhadrak |
18 |
18 |
Rs.23659856.00
18 villages |
18/
20.29 |
18 nos. Of villages |
17 nos
handedover |
|
| Keonjhar |
11+3 |
11 |
Rs19536351.00
11 Villages |
11/
9.755 |
11 nos. Of villages |
10nos
handedover |
|
Berhampur-
Taptapani- SH-17
-41 Kms |
Ganjam |
31 |
29 |
Rs. 38095299.00
28 Villages |
28/
55.138 |
29 nos. of villages |
28 villages handedover |
Digapahandi revised valuation submitted to Govt. for approval. |
| TOTAL |
|
155 |
147 |
Rs.135172670.00
146 villages |
146/
183.883 |
147 nos. of Villages |
143 |
|
|
|
|
ORISSA STATE ROADS PROJECT (YEAR-II) STATUS REPORT ON LAND ACQUISITION AS ON
28.05.2011 |
| |
Name of the Project
Corridor with Stretch |
Name of the District |
Total nos village |
Total nos village(proposal) to be sent for 4(1) Notification |
Total nos village proposals Recevied by the Revenue & DM Department |
Total nos of villages notified by Govt in Revenue Department 4(1) |
Total nos village proposals Recevied by the Revenue & DM Department U/S 6(1) |
Total amount
(Rs. Deposited) |
Total nos of village notified under Section 6(1) by Govt. in Revenue Deptt. |
Total nos of village
submited
for 7-order
to Govt |
Total No. of
village Notified by
Gov. U/s 7 |
Jagatpur-Chandbali Road, (SH-09A & SH-09)106 kms. |
Kendrapada |
62 |
53 |
53 |
53 |
51 |
154027652.00 |
50 |
48 |
17 |
| Cuttack |
K. Para Divn |
6 |
6 |
6 |
6 |
6 |
|
4 |
2 |
2 |
| CTC Divn |
38 |
35 |
35 |
35 |
34 |
|
26 |
23 |
13 |
| Total |
44 |
41 |
41 |
41 |
41 |
140691585.00 |
30 |
25 |
15 |
| Bhadrak |
7 |
6 |
6 |
6 |
5 |
1734666.00 |
5 |
|
|
| Total |
|
114 |
100 |
100 |
100 |
95 |
296453903.00 |
85 |
73 |
32 |
|
|
<<Back to Home
5.0
R & R Status (Year-1) |
|
Monthly Progress Status (Upto 28.05.2011) of 3 Corridor |
| |
| Sl. |
Name of the Package |
No. of Total PAPs as per DPR |
No. of PAPs in 1st Milestone |
Identification & Verification |
R&R Entitlement with structure valuation |
Opening of Joint Bank Account (PAP & E.E) |
| RAP |
NonRAP |
1 |
PO-1 (Bhawanipatna-Khariar Road, SH-16) |
1096 |
103 |
21 |
124 |
120 |
120 |
2 |
PO-2 (Chandabali Bhadrak Anandapur Road SH-9 & SH-53) |
3889 |
153 |
119 |
260 |
260 |
260 |
| 3 |
PO-3 (Berhampur-Taptapani Road, SH-17) |
1361 |
76 |
42 |
118 |
114 |
114 |
Total |
|
|
332 |
182 |
502 |
494 |
494 |
|
| |
|
<<Back to Home
|
| Please Refer Monthly Progress Report |
| 6.0 HIV/AIDS Awareness
(Year-1) |
|
Orissa State Roads Project has requested to Orissa State Aids Cell(OSAC)s for technical support and sensitisation of NGOs,Contractors,Consultants
and Project Mangers dealing with the Project road corridors.The process of sensitisation,
by fixing and displaying Posters and Organising road shows and campaigns, is under
process at plant sites and in vulnerable areas in each road corridor. |
|
Few Posters From the Awareness Campaigns |
|
<<Back to Home
7.0
Dispute Resolution Board (Year-1) |
| |
| As per Clause 20.2 of Volume:lI (Particular Conditions & General Conditions)
of Civil Work Contracts Dispute Resolution Board (DRB) has been
constituted. |
| |
|
As per agreement the Dispute Board visited all Year-1 Road packages
under Orisaa State Roads Project .The proceedings of DRB meeting are as follows. |
| |
|
|
| |
|
|
| |
|
|
| |
| |
| |
| |
|