M/s Pricewaterhouse Coopers in JVe with LEA Associates South Asia Pvt. Ltd, New Delhi has been engaged as the PPP Transaction Advisor Consultant to prepare the engineering, social, environmental and bidding documents after conducting necessary survey & investigation.
Name of the Road |
Status of PPP Road component as on November - 2010
Length
in Km
|
Location
( Districts) |
Scope of Project |
Civil Cost
Rs. Crore |
Total Project Cost (TPC)
Rs. Crore |
Social, Env. & Utility Shifting Cost
Rs. Crore |
Likely VGF / Concession Period (Year) |
Project Status |
Action to be Taken |
Sambalpur-Rourkela
(SH-10) |
165 |
Sambalpur, Jharsuguda & Sundergarh |
Widening from two lane to Four Lane Divided Carriage Way – Flexible Pavement with Hard Shoulder |
801 |
1270 |
213
311 Ha land
(196 Ha –R + 102 Ha-G + 13 F)
PAF-424
PDF-1791
9020 Tree
R-Revenue land
G- Govt land
F- Forest land |
24% / 30 Yrs as per Orissa Draft Toll Rules
Not viable as per MORTH-2008 toll rule
( exceed 40% grant) |
- Feasibility Study alongwith Prelim. Project. Report (PPR), design & costing complete.
- Approval of both ECI and HLCA obtained
- Draft RFQ Ready
As per GoI norms
- Draft Concession Agreement Ready as per MCA (GoI)
- Details for LAP & URP ready
- Orissa State Roads Tolls Act -2010 has been enacted approval by Orissa Legislative Assembly during August-2010.
- Administrative approval to the project obtained
- Process for land acquisition & utility shifting initiated with joint field verification and marking at site.
|
(i) Notification of Toll Rules as per Orissa Toll Act -2010
(ii) Submission of VGF application to GoI with tolling options as per Orissa State Roads Toll Act / Toll Rule -2010 after above notification.
(iii) initiation of bidding process with issue of RFQ
after obtaining in-principle approval from GoI on VGF.
(iv) Public consultation for MoEF clearance |
Joda-Bamberi (Expressway) |
18 |
Keonjhar |
Widening from single lane to 12m wide concrete pavement |
71 |
109 |
15
17..2 Ha land
14.5 Ha (R)+
2.7 Ha(F)
PAF-73
PDF-190
640 Tree
R-Revenue land
F- Forest land |
Nil / 14 Yrs. as per
Orissa Draft Toll Rules
21% / 30 Yrs as per MORTH-2008 toll rule
30 Yr. shall lead to higher degree of congestion & lower level of Service(LOS) which is not acceptable as per GoI norms . |
- Feasibility Study,
Detail Enginering Design &Costing
Complete. PPR ready.
- Details for LAP & URP ready
- ECI clearance obtained
- RFQ issued during June 2009.
- Preapplication Conference Complete.RFQ shall be received from bidders after notification of Orissa State Roads Toll Rules-2010.
|
(i) Notification of Orissa toll policy. ( Orissa Toll Act & Rules 2010)
(ii)LA & Utility shifting to be initiated after obtaining AA to the project.
(iii)State Specific provisions in MCA to be approved (consistent with Orissa toll policy- 2010) |
Koira-Tensa-Lahunipara |
49.5 |
Sundergarh |
Complete Reconstruction with 7m to 12m wide concrete pavement |
153 |
228 |
9
30.6 Ha land
18.1 Ha (R)+
12.5 Ha(F)
PAF- 06
PDF- 59
4500 Tree
R-Revenue land
F- Forest land |
Nil / 12 years as per
Orissa Draft Toll Rules
Nil / 30 Yrs as per MORTH-2008 toll rule
30 Yr. shall lead to higher degree of congestion & lower level of Service(LOS) which is not acceptable as per GoI norms . |
- Feasibility Study,
Detail Enginering Design Costing Complete.
- PPR Ready
- ECI clearance obtained.
- Revised Design is being prepared by the Consultant to avoid land acquisition in forest & ghat stretches.
- Steps are being taken at Govt. level to resolve the ownership issue of road by updating the land records.
- The road is being improved to two lane standard in stretches through Govt.’s funding.
|
This road need to be dropped from the proposed PPP mode of development as ghat and forest land prohibit options for widening and the road shall be no longer road user friendly for revenue generation in terms of tolling |
Capital Region Ring Road (CRRR) |
70 Km |
Khurda & Cuttack |
New Construction for 4-lane bituminous road in phases with 2-lane road in Phase-1 |
167
2lane
cost |
304 |
Detail survey & Engineering Investigation, LAP, URP etc. not done |
|
- ECI clearance obtained on the basis of Initial Screening Report made by ILFS
- . IDCO has been assigned to engage Consultant for detail feasibility study.
|
Feasibility Study & PPR to be done by engaging Consultant.
Budgetary support for
Rs. 158 Lakhs for Consultant as proposed by IDCO. |
Bhubaneswar-Paradeep |
|
Khurda & Jagtsinghpur |
New Construction for 4-lane bituminous road |
|
|
Detail survey & Engineering Investigation, LAP, URP etc. not done |
|
- Project is Not Viable as per Initial Screening Report of ILFS
|
|